Location: Bottesford, Leicestershire

Clients: Dyer & Butler

Type of Project: Design of new masonry headwall, a new staircase, retaining wall and lining of a masonry culvert

Scope of Services: Civil Engineering

Project Summary

Design of new masonry headwall, a new staircase, retaining wall and lining of a masonry culvert. Bottesford Culvert is a masonry culvert which runs below two running lines. The proposal detailed in the original Form F001, was to reline the existing masonry culvert using segmented GRP sections. Due to deformations with the culvert, determined from a 3D ovalisation survey, VEDA proposed a CIPP liner as an alternative to GRP sections. On the downside of the structure, the culvert was to be extended to connect to a new headwall. Furthermore a set of access stairs to the track were to be installed.