Home / Sectors / Temporary Works Sector / London Bridge Station Greens Café - Temporary Propping & Jacking

 
 
 
 

Project Description


VEDA Associates were appointed Spence as temporary works engineers for the design of the temporary works to support the existing carriage way and pedestrian access to London Bridge, to enable the demolition of the three internal load bearing masonry walls.

The contractors demolition sequence was split into three stages to enable the permanent works to installed within the tight compounds of the site.  

At each load bearing masonry wall location, a structural frame was designed using a proprietary support system, which transferred the load onto the temporary reinforced concrete strip foundations.  

 

Project Details


Project Name: London Bridge Station - Greens Café
Type of Project: Temporary Propping & Jacking
Client: Spence
Date Completed: June 2015 


Services provided:     

  • Structural Surveys & Assessments
  • Structural Engineering & Architecture
  • Civil Engineering
  • Temporary Works
 
 

Related Projects


 
 
Seven Sisters Station Raking Shores to Retaining Wall

Seven Sisters Station
Raking Shores to Retaining Wall

 
horley Station Scaffold Design Under Bridge

horley Station
Scaffold Design Under Bridge

 
Dunton Green Station Polystyrene Plant Bridge

Dunton Green Station
Polystyrene Plant Bridge